A major milestone has occurred in the construction of Panguil Bay Bridge Project with the completion of the installation of the first steel cable (1 of 10) of the Main Center Bridge. Meanwhile, the approach bridge from Tubod is now 99% completed while the approach bridge from Tangub is at 95% completion rate. The Main Center Bridge is at 50% completion. The bridge is targeted to be completed by June 2024. Photos by Zarro Cuizon.

Keep posted.