Check out the latest progress of the Laguindingan Airport Passenger Terminal Building (PTB) Expansion Project (Pre-Departure Area). As shown, the expansion has already taken shape with pre-fabricated steel structure. Once completed, it will increase its pre-departure terminal capacity to 860 passengers daily from its current 500 passengers. With a budget allocation of P32.3 million, the project is estimated to be completed by September 1, 2024.

The expansion will enable the pre-departure area to accommodate up to 860 passengers simultaneously, with the capacity to handle four jet aircraft (A321/320) and one Q4 or ATR aircraft simultaneously.

Below are screengrabs during the Senate Committee Inquiry chaired by Sen. Juan Miguel Zubiri.




Meanwhile, the rehabilitation of the airport’s six comfort rooms are still ongoing with three already been completed in the arrival area, while one has been completed in the pre-departure area. The remaining two units are expected to be completed by June 27, 2024.

This is the arrival area showing the completed units (green) and ongoing rehabilitation (red).

Below are the completed comfort rooms at the arrival area.


This one below is the comfort room in the outside arrival area.

This is the pre-departure area (2nd level) showing the completed (green) and the remaining comfort room still underhoing rehab (red).

Here’s the completed comfort room at the pre-departure area.


Keep posted.