The DPWH has finally bid out the 1.037-kilometer southwestern approach of the New Mangima Bridge along the under construction Mangima-Agusan Canyon Bypass Road in Manolo Fortich, Bukidnon. However, based on the recent pre-bid conference, the project with an approved budget contract of P86.85 million will only be a gravel road and involves right-of-way acquisition for implementation this year. When completed, motorists using the Bypass Road will avoid the Mangima Zigzag Road.
Project details are shown below. It will be completed in 405 calendar days.



Total length of the project is 1,037 meters.

Here’s the alignment of the Mangima-Agusan Canyon Bypass Road.

Below are screengrabs (from Katawa CDO Doodzkie video) of the project site.













Watch below.