South Balibago Resources, Inc. (SBRI) has just completed the testing and commissioning of its Water Treatment Plant in Iponan, Cagayan de Oro City last March 23, 2023 while pipe-laying from Iponan to intended water consumers in Youngsville Subdivision and Pag-ibig Citihomes in Igpit and Malanang, respectively, in Opol, Misamis Oriental is now at 64 percent or 2,740 out of 4,300 linear meters completed. Testing to follow after completion of pipe-laying
It can be recalled that the Cagayan de Oro City Water District (COWD) approved the purchase of bulk water supply for both Youngsville Subdivision and Pag-ibig Citihomes, two large residential communities in Opol, for 10,037,500 cubic meters for a period of 20 years.


Browse over latest photos of pipe-laying phase below.