A new 60-meter concrete bridge will be built spanning Amoros River in El Salvador City as part of the 37.6-kilometer CDO-Laguindingan Mountain Diversion Road. Amoros Bridge 2 (Contract ID No. 25K00093) will be near Sambulawan Elementary School. With an approved budget of P48.25 million, the bridge project has a contract duration of 8.5 months or 255 calendar days. Construction is expected to start early next year.

Below are screengrabs during the recent pre-bid conference by DPWH-10.

Keep posted.