PROJECT WATCH: CDO New Western Diversion Road and Macabalan-Bonbon Bridge latest update
DPWH-X Regional Director Zenaida Tan has reported that 3.02 kilometers of the 4.21-kilometer CDO New Western Diversion Road has already been concreted. Meanwhile, the 888.80-meter Macabalan-Bonbon Bridge is nearing 60.40% completion and its connecting 300-meter viaduct has just started construction. Funding for both projects were lumped into one with the CDO New Western Diversion Road … Continue reading PROJECT WATCH: CDO New Western Diversion Road and Macabalan-Bonbon Bridge latest update