Here are the latest progress update of the new CDO Eastern Diversion Road, a 4.25-kilometer 2-lane alternate road which starts at South Diversion Road (near Alegria Hills) and traverses the mountain slopes of Macasandig, Nazareth and Camaman-an towards JR Borja Extension and eventually to Lapasan. This will become a vital road in Cagayan de Oro when completed. Aerial shots courtesy of TRip ni ToniO.

As a review, here’s the alignment of the road opening.

Here’s the concreted portion of the new road.

Here’s new CDO Eastern Diversion Road with the City Memorial Park (Bolonsiri) at right.

Meanwhile, road opening is still up this point in Camaman-an area.

This section below is just near below High Ridge.

You can observe that the road alignment has been delineated.

This is where the concrete road ends.

Earthworks are still ongoing.

This road has not yet been connected to the South Diversion Road at Alegria Hills.

Completion of the road depends on the annual budget allocation by the DPWH.

Watch below.

Keep posted.